Name of the Project

Veligonda Project - Closing of Kakarla Gap by Constructing a N.O.F. Dam excavation of Link...
Project Description: Veligonda Project - Closing of Kakarla Gap by Constructing a N.O.F. Dam excavation of Link Canal and Part of Eastern Canal together with distributory system including construction of CM & CD Works
Client name: Project Administrator & Superintending Engineer, Veligonda Project Circle, Ongole. Contract Completion Date: 31-Aug-10
Consultant’s name: Revised/Expected Completion Date:
Original Contract value in INR Millions: 4591.90 Work Completed (%): 29.41%
Original Contract value in US$ Millions: 105.34 Certified amount - Actual workdone Amount (Rs. Millions) as on date: 1350.44
Contract Commencement Date: 22-Aug-05 Amount of work sub-contracted: NIL
* The project was awrded to M/s.SCL-BSCPL JV. Our Share in the Joint Venture is 35%



Name of the Project

Investigation, Design, Estimation and construction of Barrage across Champavathi river with afflux bunds...
Project Description: Investigation, Design, Estimation and construction of Barrage across Champavathi river with afflux bunds, head sluice, excavation of diversion canal including CM & CD works and tunnel, formation of earth dam to form a resorvoir with two head sluices, surplus weir, surplus course and protection bunds, excavation of right and left main canal with distributory system with CM & CD works Tarakarama Thirtha Sagaram Reservoir Project
Client name: Superintending Engineer, TTPR Circle, Vizianagaram-3. Contract Completion Date: 31-Dec-10
Consultant’s name: Revised/Expected Completion Date: EOT Submitted
Original Contract value in INR Millions: 1815.00 Work Completed (%): 20.57%
Original Contract value in US$ Millions: 39.87 Certified amount - Actual workdone Amount (Rs. Millions) as on date: 373.42
Contract Commencement Date: 24-May-06 Amount of work sub-contracted: NIL
* The project was awrded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%



Name of the Project

Package No. 27/2006 : Investigation...
Project Description: Package No. 27/2006 : Investigation, design and
1) Construction of head regulator in GBR complex and fabrication, erection of gates and hydro mechanical, electrical works and other allied works for head regulator,
2) Excavation of GNSS floow flow canal (Gorakallu Reservoir to OWK Reservoir) for the reach from km.0.000 to km.17.000 and
3) Construction of CM&CD works enroute in Kurnool District
Client name: Superintending Engineer, SRBC Circle No.2, Nandyal, Kurnool. Contract Completion Date: 30-Nov-10
Consultant’s name: Revised/Expected Completion Date:
Original Contract value in INR Millions: 2540.00 Work Completed (%): 34.97%
Original Contract value in US$ Millions: 57.57 Certified amount - Actual workdone Amount (Rs. Millions) as on date: 888.13
Contract Commencement Date: 19-Feb-07 Amount of work sub-contracted: NIL
* The project was awrded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%



Name of the Project

Construction of Somasila Swarnamukhi Link Canal from km.0.000 to km.9.500 including...
Project Description: Construction of Somasila Swarnamukhi Link Canal from km.0.000 to km.9.500 including CM & CD works, Investigation, Preparation of Hydraulic Particulars, Designs and Estimation in Nellore District
Client name: Superintending Engineer, S.S.L.C. & S.B. Circle, Dargamitta, Nellore. Contract Completion Date: 31-May-10
Consultant’s name: Revised/Expected Completion Date:
Original Contract value in INR Millions: 1026.00 Work Completed (%): 20.93%
Original Contract value in US$ Millions: 24.98 Certified amount - Actual workdone Amount (Rs. Millions) as on date: 214.74
Contract Commencement Date: 18-May-07 Amount of work sub-contracted: NIL
* The project was awrded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%