Name of the Project

Design and Construction of formation including blanketing, Major Bridges, Minor Bridges, RUBs, ROBs...
Project Description: “Design and Construction of formation including blanketing, Major Bridges, Minor Bridges, RUBs, ROBs, Supply and Spreading of Ballast and other related infrastructural works for Dedicated Freight Corridor from Chainage 14.108 Km (Near New Karwandiya) to Chainage 119.437 Km (Near New Ganj Khawaja) (Approx. 105 KMs) on Mughalsarai-Sone Nagar Section of Eastern Corridor in the states of Bihar and Uttar Pradesh in India”. (‘0.00’ Chainage starts at Km 550.245 near Sonenagar of IR track)
Client name: Dedicated Freight Corridor Corporation of India Limited, New Delhi. Contract Completion Date: 29-Feb-12
Consultant’s name: Revised/Expected Completion Date:
Original Contract value in INR Millions: 7810.60 Work Completed (%): 5%
Original Contract value in US$ Millions: 158.27 Certified amount - Actual workdone Amount (Rs. Millions) as on date: 406.94
Contract Commencement Date: 24-Feb-09 Amount of work sub-contracted: NIL
* The project was awrded to M/s.BSC-C&C JV. Our Share in the Joint Venture is 50%